INSTALLATION OF THE HUAWEI ENERGY STORAGE SYSTEM
WITH A TOTAL CAPACITY OF 107 MWh, Paltininkai (Lithuania)

LUNA 2000-213KTL-H0

PCS, 288 pcs

V2 Smart String ESS Container Structural Layout

ESS, 24 pcs

Jupiter-6000K-H1

Transformer substation, 8 pcs

DTS

8 pcs

01

STAGE

CONSTRUCTION SITE PREPARATION

  • Design and geodetic works
  • Site preparation for construction
  • Clearing and leveling of the site
  • Formwork, concreting, curing
  • Foundation pouring

02

STAGE

LAYING OF CABLE LINES

  • Trench preparation
  • Cable laying and labeling
  • Grounding circuit welding
  • Equipment installation
  • Installation of transformers, inverters, and battery containers

03

STAGE

CONNECTION

  • le terminal installation
  • Parameter testing / verification
  • Trench backfilling, compaction, and site restoration

04

STAGE

TESTING AND COMMISSIONING

  • System check
  • Commissioning and start-up activities